A practical checklist
- Read the machine meter when the maintenance event is recorded.
- Enter the observed reading, including zero when that is genuinely the reading.
- Put labour duration or an unreadable meter explanation in notes instead.
Inspection · Tractor T3 · 876 hours. Notes: “Inspection took about 45 minutes.” The hours field remains 876, not 0.75, because it records the engine meter rather than the inspection duration.
What to avoid
Never estimate a meter reading from calendar time just to fill the field. Leave it unspecified and explain the missing reading if necessary.